Oracle Project Resource Management

Oracle Project Resource Management

Oracle Project Resource Management helps to manage the capacity and deployment of people and assets for project work by finding and deploying the most qualified resources to the projects. Oracle Project Resource Management centralizes information to empower project, resource, and staffing managers to better utilize their single most critical resource: people.
This chapter describes the following test flows in Oracle Project Resource Management:
  • Project Requirement Creation to Approval
Prerequisites
None.
Profile Options
Not applicable.
Predefined Data
Not applicable.
Setup Data
Not applicable.

20.1 Project Requirement Creation to Approval

Project requirement creation to approval covers the creation of a project from a project template. It creates a requirement for the project, assigns a person to the requirement to convert into an assignment and approves the assignment of the project.
Prerequisites
  • Users with responsibilities as:
Table 20-1 Users Prerequisites for Project Requirement Creation to Approval Flow
UserResponsibility
00amasonProject Super User
00bclarkStaffing Manager
00DgeorgeResource Manger
  • Job CON600.Consultant in the job group Vision Corporation.
  • Employees with roles as:
Table 20-2 Employees Prerequisites for Project Requirement Creation to Approval Flow
Employee nameRole
00Langer, DanielEmployee for assigning to a requirement
Clark, Ms.BorisStaffing owner
George, Mr.DavidApprover for requirement
00Mason, AbrahamProject manager
  • PRC: Maintain Project Resources run to access the employees in Projects.
  • Open Accounting and GL periods for the current year.
Profile Options
Table 20-3 Profile Options for Project Requirement Creation to Approval Flow
Profile NameProfile ValueLevel
PA: Licensed to use Project Resource ManagementYesSite
PA: Availability Duration0Site
PA: Availability or Over commitment Calculation PeriodDailySite
MO: Operating UnitVision ServicesSite
MO: Security ProfileVision CorporationSite
HR: Business GroupVision CorporationSite
Predefined Data
Not applicable.
Setup Data
Table 20-4 Setup Data for Project Requirement Creation to Approval Flow
Page NameField NameField ValueComments
ProjectProject TemplateCost PlusProject type Contract is used in the template

OrganizationPJR Organization1Organization
Type- Division
Classification-HR Organization, Project Expenditure or Event Organization and Project Task Owning Organization
Project or Customer and contactsCustomer NameHilman and AssociatesCustomer must be created in Accounts Receivables
RoleNameDBAJob CON600.Consultant should be attached to the role
CalendarNamePJR Calendar 1Calendar exceptions [Holidays] defined and Shifts assigned to it [ Shift: 8x5 ] the calendar periods should fall in the project start and end dates